Set the new T-131 tool and run its first trial
You are a setter running a new tool trial with the senior setter, the toolroom and the technical team.
What has happened
New tool T-131, a two cavity air duct mould with a hydraulic core pull for Southern Cross Automotive Components, is due for its first trial under job card JC-26-3322. The tool has arrived from the toolmaker with drawings and suggested settings. Machine IM-12 has a light curtain fault logged in the WHS register and is tagged out, so the trial is likely to move to IM-10, which has a different platen size and controller. The Tooling and Maintenance Manager and the Technical, Quality and WHS Manager will attend. The trial must be planned with a Job Safety Analysis, the die set under lock out to the procedure, the process built up from the toolmaker's data and everything recorded on the trial report.
Deliverables
- Machine selection record and Job Safety Analysis
- Isolation and die set record
- Draft Process Setting Sheet with starting settings
- Completed Production Trial Report with measurements and decision
- Updated tool register and job card entries
Documents to use
Systems to use
Tool and Die Register
Holds every mould, extrusion die, calibrator and cable die with its version, condition, service history, cavity or size details and storage location.
WHS Incident and Hazard Register
Records injuries, near misses, hazards, chemical events, burns and property damage at all sites and on customer sites with investigation and actions.
Production Job Cards
Tracks every production, trial and site service job from release through setup, first-off approval, running, inspection and packing.
Quality Nonconformance Register
Records nonconforming product, process deviations, cable test failures and customer complaints with disposition and corrective action.
Units of competency
Current on training.gov.au for the Plastics, Rubber and Cablemaking as at 10 September 2026.
PMBPREP304ESet a die for injection moulding productionPMBPROD430ETrial a new injection moulding diePMBTECH301EOptimise polymer processing operationsPMBTECH406EDiagnose production equipment problemsPMBPROD385EProgram computer-controlled equipmentQualifications
PMB30121Certificate III in Polymer ProcessingPMB40121Certificate IV in Polymer TechnologyWhat to look for
Evidence guide
Look for the machine decision made from the register entries rather than assumed, a Job Safety Analysis that covers the core pull and the unproven tool, isolation steps that include hydraulic core energy, and a trial record where every change has a reason and an effect. Measurements must be per cavity against the drawing. The decision must be agreed with the technical team, not made alone.